Project required construction of detention basin
while restoring 3 acres of riparian habitat. Construction of detention
basis required construction of 1700LF of 25' high levee embankment.
To draw water into the basin from an existing stream a 200' box
culvert with weir structure and concrete spillway was attached to
the existing structure under the roadway. Project also entailed
construction of a recreation area including biking and hiking trails
with a parking lot.
|