U.C. Davis Design Build WWTP
Location: Davis, CA
Client: University of California - Davis
Completion Date: January 2008

Design build delivery system was utilized
to increase the campus wastewater facility from 6.3 MGD to 9.4 MGD. The
major components of work consisted on constructing a 70' secondary clarifier,
a new disk filter, a new UV channel with associated disinfection equipment,
the addition of one effluent pump, the addition of three influent pumps,
and all electrical and instrumentation upgrades associated with the plant
expansion.
A unique feature of this project is that this
was the first design build delivery method used for their infrastructure
improvements by the U.C. System.

|